TC Energy Anticipates Significant Cost Increase for Coastal GasLink Natural Gas Pipeline
The company targets mechanical completion of the natural gas pipeline by the end of the current year.
SEATTLE (Oil Monster): TC Energy Corp. anticipates significant increase in expected costs for the Coastal Gas Link (CGL) natural gas pipeline in Western Canada. The price increase is based on challenges on multiple fronts. The 416-mile pipeline is intended to connect gas supply from the Western Canadian Sedimentary Basin (WCSB) with the LNG Canada terminal.
ALSO READ:
Turkiye Signed Historic Natural Gas Deal with Oman
EIA: Proved Reserves of U.S. Natural Gas Surged 32% in 2021
The announcement to this effect by the company’s management noted that the project is now expected to cost $10.9 billion, significantly higher from the earlier forecast of $8.4 billion. The company cited challenging conditions in the Western Canadian labor market, contractor underperformances, drought conditions and erosion and sediment control challenges as the reasons for the cost increase.
The company targets mechanical completion of the natural gas pipeline by the end of the current year. The commissioning and clean-up work may extend into 2024 and 2025. The construction of the pipeline is nearly 83% complete and the entire route has been cleared, the management said.
François Poirier, CEO, TC Energy Corp. stated that the company is disappointed with the increase in the Coastal GasLink project costs.