Cascadura Natural Gas Facility Expects First Production in June

In its update on the construction status of the facility, Touchstone Exploration Inc. noted that it has completed around 80% of the communication tower.

Cascadura Natural Gas Facility Expects First Production in June

SEATTLE (Oil Monster): The National Gas Company of Trinidad & Tobago Ltd notified that the first gas production from the Cascadura natural gas and associated liquids facility is expected to be received by it by end-June this year, said Calgary, Canada-based Touchstone Exploration Inc.

The oil and gas major said that it remains on track to attain successful completion of the Cascadura facility before the above said date, so as to ensure that it could commence production as soon as NGC notifies it of its readiness to receive first gas.

In its update on the construction status of the facility, Touchstone Exploration Inc. noted that it has completed around 80% of the communication tower. Almost 90% of the pipe racks has been assembled. Also, all process equipment are being acquired. In addition, the on-site condensate tanks are almost 65% complete.

Paul Baay, Chief Executive Officer noted that the company is encouraged to have received an expected first gas date from NGC. This will help it to plan the final phase of various work streams to minimize costs and optimize services. The first date happens to be later than what the company has been anticipated. It expects to complete drilling the Royston-1X well at the earliest and prepare its next development locations in Cascadura, he added.